• Late

    2020

    Target for first phase operators opening for business.

  • Late

    2019

    Target for commencing phase one construction.

  • Summer

    2019

    Planning Application decision expected.

  • January

    2019

    Site clean up commences.

  • September

    2018

    Outline planning application submitted for UK’s first truly multi-model superhub to create 4,500 jobs.

  • November

    2017

    Completion of the former Coryton Oil Refinery demolition programme.

  • April

    2017

    Planning consent granted for the remediation and decontamination of 114 acres of the site.

  • November

    2016

    The demolition of one of the refinery chimneys in November 2016, with the retention of another to serve as a landmark for the future Thames Enterprise Park.